kitchen renovation timeline — How Long Does a Kitchen Renovation Take? Realistic GTA Timeline (2026)
Kitchens

How Long Does a Kitchen Renovation Take? Realistic GTA Timeline (2026)

Grand Craft TeamMarch 12, 20266 min read

Most homeowners think a kitchen renovation takes 6–8 weeks. The reality, after running hundreds of GTA kitchens: 4–6 months end-to-end. Here's the real phase-by-phase timeline and where projects actually run over.

Most homeowners walk into a kitchen renovation expecting it to take 6–8 weeks. The reality, after running hundreds of kitchen renovations across the GTA: a properly executed full kitchen renovation runs 4–6 months end-to-end. Here's the realistic timeline by phase, where projects actually run over, and how to plan your life around the reality (not the marketing).

Realistic end-to-end kitchen renovation timeline (GTA)

A typical full kitchen renovation in the GTA takes 16–26 weeks (4–6 months) from first design meeting to finished kitchen. This breaks down into four phases that overlap partially:

  • Phase 1: Design and selections (4–8 weeks)
  • Phase 2: Cabinet and material lead times (6–14 weeks, runs in parallel with phase 3)
  • Phase 3: Permits (4–10 weeks, runs in parallel with phase 2)
  • Phase 4: On-site construction (6–14 weeks)

The longest phases — material lead times and permits — happen in parallel, not sequentially. The actual on-site construction is shorter than most people expect, but the lead-up is longer.

Phase 1 — Design and selections (4–8 weeks)

Most projects spend longer here than expected. Design and selections involves:

  • Initial consultation and site measure
  • Layout design and 3D renderings
  • Cabinet specification (door style, finish, hardware, interior accessories)
  • Countertop selection (slab viewing if natural stone or premium quartz)
  • Flooring, tile, paint, lighting, and plumbing fixture selection
  • Appliance specification (dimensions matter — they drive cabinet design)
  • Final pricing and contract

What slows it down: indecision (especially among couples), waiting on appliance availability, custom-tile lead times, and back-and-forth design revisions. The fastest design phases we run are 4 weeks; the longest stretch to 12 weeks when clients are evaluating options.

Phase 2 — Cabinet and material lead times (6–14 weeks)

Once selections are locked, materials need to be ordered:

  • IKEA / RTA cabinets: 1–3 weeks
  • Mid-range semi-custom cabinets (Cabico, Decor): 6–10 weeks
  • Full-custom cabinets (AyA, custom shops): 10–16 weeks
  • Quartz countertops: 2–4 weeks after cabinet install template
  • Marble or imported stone: 3–6 weeks
  • Custom range hoods or millwork: 4–10 weeks
  • Specialty appliances (Wolf, Sub-Zero, Miele): 6–14 weeks (some at 20+ weeks for backorders)

Cabinet lead times have been the dominant constraint in GTA kitchens for the last several years. Plan around them — there is no shortcut.

Phase 3 — Permits (4–10 weeks)

For renovations requiring permits — which is most GTA kitchen renovations involving plumbing or electrical changes — the permit process runs alongside material ordering. See our full breakdown of home renovation permits in Ontario for fee structures and what triggers a permit. Typical timing: permit drawings prep takes 2–4 weeks, municipal review runs 4–10 weeks, and issuance is same-day after approval. If your project requires a Committee of Adjustment variance, add 3–6 months. This is rare for kitchens but common for additions.

Phase 4 — On-site construction (6–14 weeks)

The visible part of the renovation. A typical 200 sq ft mid-range kitchen renovation:

  • Week 1: Demo and site protection — floor protection installed, dust barriers up, existing kitchen demolished, debris removed
  • Week 2–3: Rough-in — plumbing, electrical, and HVAC roughed-in to new locations; new framing if walls moved
  • Week 4: Inspection and drywall — rough-in inspection, drywall hung, taped, sanded, primed
  • Week 5–6: Cabinets and flooring — flooring installed, cabinets installed, doors and drawers aligned
  • Week 7–8: Countertop template, fab, and install — template after cabinets are set, then 2–4 week fab wait, then install
  • Week 9–10: Tile, plumbing fixtures, lighting — backsplash tile, plumbing fixtures connected, light fixtures installed, electrical trim
  • Week 11+: Punch list and final inspection — touch-ups, final cleaning, deficiencies addressed, final building inspection

Smaller kitchens compress to 6–8 weeks; high-end custom kitchens stretch to 14–20 weeks (longer countertop fab, more custom millwork, more inspections).

Where projects actually run over

The four most common timeline-killers we see:

  • Countertop template-to-install gap: the 2–4 week wait after templating is the longest "nothing visible is happening" stretch — homeowners feel the project has stalled
  • Custom appliance backorders: a 20-week backorder on a Wolf range can stop the entire kitchen, since cabinet and tile work depends on appliance dimensions
  • Mid-project scope changes: "while we're at it, can we also..." adds 1–4 weeks per scope change
  • Hidden structural finds: rotted subfloor, knob-and-tube wiring, cracked supply lines — common in pre-1980 GTA homes; add 1–3 weeks each

The honest truth: a 4-month estimate for a complex GTA kitchen renovation is optimistic. Plan for 5–6 months and you'll rarely be disappointed.

How to live without a kitchen for 3–4 months

You can absolutely survive a kitchen renovation while living in the home — most of our clients do. A few tips:

  • Set up a temporary kitchen (basement, dining room corner, garage with insulation): mini-fridge, induction burner, microwave, sink-substitute (large stockpot for dishes)
  • Pre-cook and freeze 3–4 weeks of meals before demo starts
  • Plan one restaurant night per week as a deliberate break — it preserves morale
  • Use a separate door for trades if possible — keeps the family living space cleaner
  • Communicate with kids: "the kitchen will look like a construction site for 3 months" — kids handle this better than spouses do

Smaller kitchens, condo renovations, or projects with very young kids often justify temporarily moving out. Budget for 8–14 weeks of a short-term rental if you choose that route.

Kitchen renovation timeline FAQs

Can a kitchen renovation be done in less than 8 weeks?

Only the on-site construction portion can fit in 6–8 weeks, and only for smaller kitchens with stock cabinets, no permit, and no structural changes. The full project — design, ordering, permits, construction — almost always takes 4–6 months minimum in the GTA. Any contractor promising "8 weeks total" is either cutting corners or not being realistic.

What's the longest part of a kitchen renovation?

Cabinet lead times are usually the longest single phase — typically 6–14 weeks for semi-custom or full-custom cabinets in the GTA. This runs in parallel with permits and design selections, so it doesn't add 14 weeks linearly to the timeline, but it does set the floor for when on-site construction can begin.

Should I move out during a kitchen renovation?

Most GTA homeowners stay in the home during a kitchen renovation, setting up a temporary kitchen in another room. Moving out is more common when there's only one bathroom near the kitchen, when young kids are in the home, or for high-end full-custom kitchens that take 14+ weeks of on-site work.

How can I speed up a kitchen renovation?

Three biggest accelerators: lock all design and material selections before signing the contract (eliminates mid-project decisions), choose stock or quick-ship cabinets (1–3 week lead times instead of 10–16), and avoid scope changes once construction begins. Each one cuts 2–6 weeks from the timeline.

TagsKitchen RenovationProject TimelineProcess

Ready to start your renovation?

Grand Craft Renovations specializes in custom renovations across Toronto, Richmond Hill, Markham, Vaughan, and the GTA. See our home remodeling & renovation services or request a free consultation — no obligation.